New Library Building Update




In June:


  • Fencing went up and they have trenched aournd the perimeter of the site to catch any construction run-off.


  • The city water department is putting in the new drainage system what will be located under the parking lot.


  • Demolition should begin around June 27.


In July:




  • Ground is being prepared for the foundation that will be poured mid July


  • Complete demolition of the Homann Karate Do building